In February 2015 we began the detailed demolition of the Q21 building located in the Pearl District of Portland, Oregon. In working with Andersen Construction and YBA Architects to maintain the integrity of the structure, 75% of an existing warehouse was brough down as well as site excavation, earthwork, and site utilites installation to make way for a mixed-use structure that will host 163 apartment units, local shopping, and restaurants.

 

Visit the link below to check out the Q21 structure

http://liveq21.com/

 

 

Estimator & Project Manager:

Bruce McIntosh

Project Foreman:

Carl Sandell

Personnel:

5-10 laborers & operators.

Timeframe:

18 Months